The Northland local road network has suffered approximately $89 million worth of damage from at least ten different significant weather events since July 2022, with an estimated $34 million of this in the Kaipara District.
Timeframes given are our best estimates based on current evaluations and may change as we complete investigations and finalise designs.
Slip repair schedule
Below is an overview of the land slip locations in the Kaipara District, their repair status and estimated timing for construction.
Updated 1 July 2024
Road | Start | End | Length | Repair status | Estimated construction start |
ARARUA RD [KDC] ARCADIA RD BULL RD [KDC] COLVILLE RD CURNOW RD HOUTO RD [KDC] HOUTO RD [KDC] MAITAHI RD PUKEHUIA RD PUKEHUIA RD PUKEHUIA RD PUKEHUIA RD PUKEHUIA RD PUKEHUIA RD TINOPAI RD WHAKAPIRAU RD AVOCA EAST RD AVOCA RD MANGARATA BLOCK RD MASON RD [KDC] MURRAY RD [KDC] WAINUI RD WAINUI RD AVOCA NTH RD AVOCA NTH RD MAHUTA GAP RD MAHUTA GAP RD GOLDEN STAIRS RD KAIWAKA MANGAWHAI RD LAWRENCE RD MANGAWHAI RD MURRAY RD [KDC] PAHI RD POUTO RD PUKEHUIA RD BICKERSTAFFE RD BICKERSTAFFE RD MANGAWHAI RD PAPAROA OAKLEIGH RD PAPAROA OAKLEIGH RD WAIRERE RD TROUNSON PARK RD |
2974 220 233 154 1237 2783 3636 1636 17998 16964 19991 15853 16616 2988 16124 8275 185 5640 2370 2086 2655 149 5221 115 3800 1415 1672 4828 1080 1569 2528 1655 4036 40944 15769 4591 9164 806 5255 5432 1024 3962 |
2989 241 273 189 1282 2833 3654 1646 18014 17004 20082 15900 16763 3013 16190 8315 208 5674 2385 2136 2685 179 5226 144 3850 1430 1687 4848 1140 1592 2578 1675 4109 40972 15804 4641 9204 821 5296 5456 1039 4028 |
15 21 40 35 45 50 18 10 16 40 91 47 147 25 66 40 23 34 15 50 30 30 5 29 50 15 15 20 60 23 50 20 73 28 35 50 40 15 41 24 15 66 |
Construction Design Monitor Design Design Design Design Monitor Construction Construction Construction Construction Construction Construction Design Design Monitor Monitor Monitor Monitor Monitor Monitor Monitor Planning Planning Planning Planning Planning Planning Planning Planning Planning Planning Planning Planning Design Design Design Design Design Planning Design |
Q2 - Autumn 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 Q2 - Autumn 2024 Q2 - Autumn 2024 Q2 - Autumn 2024 Q2 - Autumn 2024 Q2 - Autumn 2024 Q2 - Autumn 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 TBC – Post 2024 Q4 - Spring 2024 Q1 - Summer 2025 Q4 - Spring 2024 Q4 - Spring 2024 Q4 - Spring 2024 Q4 - Spring 2024 Q4 - Spring 2024 Q1 - Summer 2025 Q4 - Spring 2024 Q4 - Spring 2024 Q4 - Spring 2024 Q4 - Spring 2024 Q4 - Spring 2024 Q4 - Spring 2024 Q3 - Winter 2024 |
Estimated construction timing:
- Q1 (summer): January – March 2024
- Q2 (autumn): April – June 2024
- Q3 (winter): July – September 2024
- Q4 (spring): October – December 2024.
Learn more about land slip repairs.